Carriageway resurfacing and drainage works along the A33 are programmed to start on 16th September 2019 and are expected to last up to 6 weeks.

In order to undertake the works safely it will be necessary to close the road and traffic will be diverted along the A339, A30 & B3349. Due to the impact the closure will have on traffic and to minimise disruption, it is also necessary to carry out this work at night between 10pm and 6am. The road will be open during the day and at weekends. 

Minor drainage works will be completed between the Thornhill Way junction and Turgis Green (BP garage) which will be carried out between 16th September and 1st October, and will be followed by the carriageway resurfacing between 2nd and 22nd October 2019.