Scheduled road widening on A33 begins 27th July 2020

The approved A33/South Drive junction improvement scheme will commence on 27 July 2020 for an approximate duration of 14 weeks.  (The expected duration of the works has increased due to the change in working practices that are required for the contractor to be able to meet the requirements of a ‘covid safe’ site).  Efforts will be made to minimise the impact of the scheme on A33 traffic, with much work completed under minimal traffic management, mainly off-peak traffic signals where required with a period towards the end of the works of approximately 3 weeks when traffic lights will need to be in operation 24 hours a day.  Up to 5 nights of road closures will be required to complete surfacing operations and a signed diversion route will be in place during these times.

Scheme website here for information.